International Airport Terminal Houari Boumediene Algiers Airport activity
 
International Airport Terminal Houari Boumediene Algiers Airport activity

The customer
The EGSA "Establishment of Management of Airport Services Algiers" under the supervision of the Ministry of Transport, manages, develops and operates the public air traffic airports. The EGSA is involved in the management of seventeen airports located south and center of the country.
The project
New international airport terminal and Vip Lounge Algiers, amount 150M€, annual traffic flow 6million pax 
Project supervisor: ADPI
Work allotted to the head contractor CSCEC (China State Construction Engineering Compagny).
Cegelec Infrastructures was selected to carry out electrical installations, and LV systems security, access control, fire protection, airport information system hardware and software.
 
Cegelec Infrastructures performance
- Detailed technical and functional specifications, drawing
- Management system solution for access control and security system CCTV, LAN network,
- Public address, fire detection, téléphone and building management system.
- Airport system management, FIDS, CUTE, BRS
- Electrical distribution, transformer, switchboard , UPS, panel, lighting
- Supply and delivery up to the site
- Commissioning
- Training & maintenance
 
Project key data :
 5MVA power installed
 Low Voltage cabinets: 220
 Lighting fixture: 10 000
 Check in desk: 60
 TFT monitor: 220
 Cameras: 240
 Loud speaker :700
 Fire détection: 1300 points
 Year : 2004 - 2006
 


GCCIA Project - Middle Est
 
GCCIA Project - Middle Est

The customer


The Gulf Cooperation Compagny Interconnection Authority (GCCIA) is a joint stock compagny subscribed by the six Gulf States whose articles of Association and By Laws were approved by Royal Decree on july 29, 2001.Head Office is located in the city of Al Khobar Saudi Arabia.

The project
 
The Gulf Cooperation intends to procure and install a physical Security System at its various substations and installations.The objectives of the physical security system is to monitor, detect, assess, trace and video record intrusion alarm situations, and to control personnel access to the Facilities.

Cegelec performance
  • Detailed technical and functional specifications
  • Centralized solution for Access Control and Security System (Fiber Optic Fence Sensor System, CCTV, Enhanced Detection System, Switch, with the global supervision software Evolynx, first HTTPS secure WEB 2.0 security solution.
  • Electrical sub distribution, panel , UPS
  • Supply and delivery up to the site of the customer in 5 countries
  • Execution of all the works of installation and assembly for FOSS,CCTV, A Control in the High voltage electrical area
  • Commissioning
  • Training & maintenance
     
Project key data :
  • 5 countries supervised
  • Redundant system between 2 countries
  • Security Solution & global supervision with Iplerflex Evolynx software
  • Installation Card Reader : 290
  • Cameras: 222
  • Perimeter fence protected : 16Kms
  • Year : 2011 - 2013
  • Amount of Contract :10M US$

 

 

Tags: CCTV, Security


Photovoltaic power plant at Miradoux
 
Photovoltaic power plant at Miradoux

34,300 solar panels at Miradoux (8 MWp): Cegelec Energy designed and built one of France’s biggest photovoltaic power plants, which was officially opened during the year. This plant alone will meet the electricity needs of around 4,500 households. Cegelec Energy teams will operate the infrastructure for several years. This major project establishes the group as a key player in the development of renewable energy.

 

Tags: Photovoltaic


Cegelec Brazil wins Vallourec maintenance contract
 
Cegelec Brazil wins Vallourec maintenance contract

Cegelec Brazil has been selected by Vallourec & Sumitomo Tubos do Brasil (VSB) to carry out the electromechanical maintenance of its Jeceaba plant in the state of Minas Gerais. The plant manufactures seamless tubes for the oil and gas sector. The three-year contract, with an initial value of more than €10 million, will employ some 150 people specialising in electricity, instrumentation, mechanical engineering, welding and pipes. The Cegelec Brazil teams are also tasked with scheduling and executing corrective and preventive maintenance.

 

Tags: Maintenance


Cegelec Space and the 57th launch of Ariane 5
 
Cegelec Space and the 57th launch of Ariane 5

During the night of 22 to 23 April 2011, the 57th Ariane 5 took off from the Centre Spatial Guyanais (Kourou) and launched two telecommunications satellites into orbit. Cegelec Space teams (160 employees) have been working at the space centre since 1968, participating in all Ariane 5 launches. They are responsible for the operation and maintenance of the fluid and mechanical systems, payload preparation and the construction and fit-out of changes to the base’s facilities.


A first light rail system in Le Havre
 
A first light rail system in Le Havre

Cegelec Infrastructures & Mobility is installing the high current equipment for Le Havre’s first light rail system, which will be brought into service at the end of 2012. The contract calls for the installation of eight traction sub-stations, three auxiliary stations, and smoke exhaust and ventilation systems for the 700 metre Jenner Tunnel. For this project, Cegelec is deploying a unique system to recover the energy generated when the trains brake.

 

Tags: Transports, Tramway


Construction and optimization of compressor stations for natural gas
 
Construction and optimization of compressor stations for natural gas

Completion of two contracts within the framework of the modernisation of GRTgaz’s natural gas compressor stations. As part of the consortium led by Litwin, Cegelec was tasked in 2006 with optimising five existing stations. Two years later, it was asked to build a new station at Saint Victor near Montluçon.